Hong Kong suspends contractors over Queen Mary Hospital lift defects
Authorities say 24 of 28 lifts in new block are affected, delaying the launch of clinical services until repairs are completed
Hong Kong authorities have suspended the main contractor and lift subcontractor working on a new clinical block at Queen Mary Hospital from tendering for public works after serious defects left most lifts unreliable and delayed the launch of services.
An engineer and a lawmaker said on Saturday that the extent of the defects was “extremely rare” in Hong Kong and unreasonable, while the government’s decision to temporarily stop the firms from tendering for other projects was appropriate.
The Architectural Services Department said in a social media post late on Friday that the contractors’ poor performance had been recorded in assessment reports.
It added that the firms would need to bear the full cost of remedial works and could face claims for losses arising from delays to the HK$15.15 billion (US$1.93 billion) redevelopment project at the hospital in Pok Fu Lam.